6
Projects Approved
₹ 20.43Cr.
Total Cost of Approved Projects
₹ 7.44Cr.
Amount Released to City
9.00%
Physical Completion
Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Landscape Garden by using treated water from waste water treatment plant at Banki Muhana at Puri. 3.66 0.73 Mar, 2017 Mar, 2018 30 Work In progress
2 Landscape development of Shri Jagannatha Ballabh Matha Garden at Puri 8.80 3.52 Nov, 2017 Nov, 2017 0 Selection of Contractor is in process
3 Landscape development etc along the River Front Atharnala at Puri 1.99 0.79 Apr, 2017 Apr, 2018 30 Work In progress
4 Improvement and facades up-gradation of Bada Odiya Matha and Ganga Mata Matha at Puri 1.84 0.73 Aug, 2017 Sep, 2018 5 Selection of Contractor is in process
5 Revival of Pokharis, Ponds located in 7 Jagaghara at Puri 1.14 0.45 Aug, 2017 Sep, 2018 5 Work in progress
6 Retrofitting of building facades along the Parikrama Marg (periphery) of Shri Jagannatha Temple at Puri 2.97 1.19 Aug, 2017 Sep, 2018 2 Work in progress