6
Projects Approved
₹ 20.43Cr.
Total Cost of Approved Projects
₹ 11.12Cr.
Amount Released to City
44.00%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Landscape Garden by using treated water from waste water treatment plant at Banki Muhana at Puri. 3.66 3.66 Mar, 2017 Jun, 2018 90 Work In progress
2 Landscape development of Shri Jagannatha Ballabh Matha Garden at Puri 8.80 3.52 Dec, 2017 Jun, 2018 20 Work In progress
3 Landscape development etc along the River Front Atharnala at Puri 1.99 1.54 Apr, 2017 Jun, 2018 50 Work In progress
4 Improvement and facades up-gradation of Bada Odiya Matha and Ganga Mata Matha at Puri 1.84 0.73 Aug, 2017 Oct, 2018 40 Work In progress
5 Revival of Pokharis, Ponds located in 7 Jagaghara at Puri 1.14 0.45 Aug, 2017 Oct, 2018 60 Work in progress
6 Retrofitting of building facades along the Parikrama Marg (periphery) of Shri Jagannatha Temple at Puri 2.97 1.19 Aug, 2017 Oct, 2018 50 Work in progress