6
Projects Approved
₹ 200296639.82Cr.
Total Cost of Approved Projects
₹ 10.73Cr.
Amount Released to City
53.30%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Retrofitting of building facades along the parikrama Marg periphery of Shri Jagannath temple at puri 16644752.98 1.19 Sep, 2017 Nov, 2018 65.00 Work is progress
2 Revival of pokhari in 11 nos jagaghara 7997126.27 0.79 Sep, 2017 Nov, 2018 60.00 Work in progress
3 Landscape devlopment etc along the river front Atharanala at puri 53235514.00 1.54 Dec, 2017 Nov, 2018 45.00 work in progress
4 Landscape Devlopment of Shri jagannatha Ballabh Matha Garden at Puri 65786868.82 3.52 Dec, 2017 Nov, 2018 35.00 Work in progress
5 Improvement of facades up gradation of bada Odia maths & Ganga Mata maths at puri 18231485.75 0.73 Sep, 2017 Nov, 2018 40.00 Work is progress
6 Development of landscape garden by using treated water from waste water treatment plant at Banki muhana at puri 38400892.00 2.93 Mar, 2017 Nov, 2018 96.00 Work in progress