Sample Dashboard
4
Projects Approved
₹ 33.37Cr.
Total Cost of Approved Projects
₹ 11.23Cr.
Amount Released to City
4.25%
Physical Completion
Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
Development of Vrindawan Parikrama Marg. 10.56 2.11 May, 2017 May, 2017 15 Work in progress
DPR for Krishna Janmabhoomi Precinct 13.02 5.20 May, 2017 May, 2017 2 Work in progress
DPR for Revitalization of the Historic Chatta Bazaar at Mathura 6.15 2.46 0000-00-00 0000-00-00 0 Selection of Contractor is in process
DPR for Rejuvenation of the Historic Vishram Ghat at Mathura 3.62 1.45 0000-00-00 0000-00-00 0 Selection of Contractor is in process