3
Projects Approved
₹ 199958000.00Cr.
Total Cost of Approved Projects
₹ 14.17Cr.
Amount Released to City
76.31%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Developement and Infrastructure Up gradation around Kamatchiamman Temple Zone 24600000.00 0.98 Feb, 2018 Oct, 2018 50.00 -
2 Developement and Infrastructure Up gradation around Varadharaja Perumal Temple Zone 76386000.00 5.74 Aug, 2016 Oct, 2018 80.00 -
3 Developement and Infrastructure Up gradation around Ekambareswarar Temple Zone 98972000.00 7.44 Aug, 2016 Oct, 2018 80.00 -