7
Projects Approved
₹ 34,62,72,918.00 Cr.
Total Cost of Approved Projects
₹ 20,06,00,583.00 Cr.
Amount Released to City
50.40%
Physical Completion

Progress till January 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Connecting pathway- Dungeshwari hill to Mahabodhi temple (Zone-6) at Bodh Gaya 10,42,09,030.00 7,36,83,612.00 Jun, 2018 Feb, 2019 60.00 Site work in Progress
2 Development of Ghats and Sarovars at Gaya: Brahmsat and Baitarani Sarovar. 5,86,56,678.00 4,69,25,343.00 Oct, 2017 Jan, 2019 68.00 Site work in Progress
3 Development of Vishnupad temple complex and Ghats (Zone-1) at Gaya 8,78,35,350.00 3,51,34,140.00 Apr, 2018 Feb, 2019 30.00 Site work in Progress
4 Beautification and Development of Sita Kund Temple complex and Ghats, Gaya 5,99,00,000.00 1,63,20,000.00 Oct, 2018 Jan, 2019 45.00 Site work in Progress
5 Beautification and Development of Pitamaheshwar Sarovar, Gaya 1,95,00,000.00 64,00,000.00 Oct, 2018 Feb, 2019 30.00 Site work in Progress
6 Construction of Four Welcome Arch (Entrance Gates) for Gaya 0.00 92,00,000.00 Oct, 2018 Dec, 2018 0.00 Work not started yet
7 Development of Akshay Vat Complex (Zone-2) at Gaya 1,61,71,860.00 1,29,37,488.00 Oct, 2017 Jan, 2019 80.00 Site work in Progress. Structure work has been completed. Stone cladding work is ongoing.
  Total 34,62,72,918.00 20,06,00,583.00