4
Projects Approved
₹ 34.69Cr.
Total Cost of Approved Projects
₹ 16.87Cr.
Amount Released to City
14.00%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Ghats and Sarovars at Gaya: Brahmsat and Baitarani Sarovar. 5.86 4.69 Oct, 2017 Oct, 2018 45 Work in progress
2 Development of Ghat and Vishnupad temple complex (Zone-1) at Gaya 8.78 3.51 Mar, 2018 Nov, 2018 8 Work in progress
3 Development of Akshay Vat Complex (Zone-2) at Gaya 1.61 1.29 Oct, 2017 Jun, 2018 70 Work in progress
4 Development of Connecting pathway- Dungeshwari hill to Mahabodhi temple (Zone-6) at Bodh Gaya 18.42 7.36 Mar, 2018 Nov, 2018 2 Work in progress