6
Projects Approved
₹ 28,20,04,551.00 Cr.
Total Cost of Approved Projects
₹ 18,48,30,200.00 Cr.
Amount Released to City
54.97%
Physical Completion

Progress till January 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Zone 01 : Temple square 2,13,84,681.00 2,14,00,000.00 Aug, 2017 Nov, 2018 100.00 -
2 Zone 02 : Vegetable Market square 2,88,75,379.00 2,49,94,938.00 May, 2017 Dec, 2018 95.00 -
3 Zone 03 : Siddhanath Mahadev Temple precint 2,51,85,139.00 2,54,21,789.00 Apr, 2017 Dec, 2018 90.00 -
4 Zone 04 : Iskon Gate Darshan Path 5,63,70,128.00 4,49,84,052.00 Jun, 2017 Dec, 2018 85.00 -
5 Zone 05 : Teen batti - Darshan Path 1,53,89,224.00 1,41,29,421.00 Jul, 2017 Nov, 2018 100.00 -
6 Bet Dwarka Darshan Circuit 13,48,00,000.00 5,39,00,000.00 May, 2018 Mar, 2019 15.00 -
  Total 28,20,04,551.00 18,48,30,200.00