6
Projects Approved
₹ 32.40Cr.
Total Cost of Approved Projects
₹ 18.49Cr.
Amount Released to City
35.00%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Vegetable market square 3.71 2.49 Feb, 2017 Jun, 2018 55 Work In Progress
2 Development of Sidheshwar Mahadev Precinct 3.23 2.54 Feb, 2017 Jun, 2018 60 Work In Progress
3 Development of Darshan Path – Teen Batti 1.97 1.41 Feb, 2017 Jun, 2018 55 Work In Progress
4 Development of heritage zone 01 Dwarkadhish temple square 2.74 2.14 Feb, 2017 Jun, 2018 70 Work In Progress
5 Development of heritage zone 04 Main Processional Street (Darshan Path) from Iskon Gate to Dwarkadhish temple 7.24 4.49 Feb, 2017 Jun, 2018 60 Work In Progress
6 Development of Bet Dwarka Darshan Circuit 13.48 5.39 May, 2018 Oct, 2018 5 Work In Progress