6
Projects Approved
₹ 301564377.00Cr.
Total Cost of Approved Projects
₹ 18.34Cr.
Amount Released to City
44.79%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Zone 01 Temple square 21384681.00 1.99 Aug, 2017 Oct, 2018 90.00 -
2 Zone 02 Vegetable Market square 28875379.00 2.49 May, 2017 Oct, 2018 80.00 -
3 Zone 03 Siddheswar Mahadev Temple Precinct 25185139.00 2.54 Apr, 2017 Oct, 2018 80.00 -
4 Zone 04 Iskon Gate Darshan Path 56370128.00 4.49 Jun, 2017 Oct, 2018 85.00 -
5 Zone 05 Teen batti - Darshan Path 15389224.00 1.41 Jul, 2017 Oct, 2018 90.00 -
6 Bet Dwarka Darshan Circuit 154359826.00 5.39 May, 2018 Apr, 2019 7.00 -