6
Projects Approved
₹ 32.40Cr.
Total Cost of Approved Projects
₹ 11.18Cr.
Amount Released to City
5.00%
Physical Completion
Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Vegetable market square 3.71 0.74 Nov, 2017 Nov, 2017 5 Work In Progress
2 Development of Sidheshwar Mahadev Precinct 3.23 0.64 Nov, 2017 Nov, 2017 5 Work In Progress
3 Development of Darshan Path – Teen Batti 1.97 0.39 Nov, 2017 Nov, 2017 0 Work In Progress
4 Development of heritage zone 01 Dwarkadhish temple square 2.74 1.09 Nov, 2017 Nov, 2017 0 Work In Progress
5 Development of heritage zone 04 Main Processional Street (Darshan Path) from Iskon Gate to Dwarkadhish temple 7.24 2.89 Nov, 2017 Nov, 2017 7 Work In Progress
6 Development of Bet Dwarka Darshan Circuit 13.48 5.39 Nov, 2017 Nov, 2017 0 Contractor Selection is in process