4
Projects Approved
₹ 18.67Cr.
Total Cost of Approved Projects
₹ 5.39Cr.
Amount Released to City
23.00%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Underground Drainage for Old Bdami Town 0.51 0.37 Jul, 2017 Jun, 2018 65 Work In Progress
2 Zero Waste Management for Badami Town 2.30 1.84 Aug, 2017 Jun, 2018 80 Work In Progress, for remaining components, CPWD assigned work of project implementation
3 Improvement of Historic, Vernacular Building Fa├žade and Streetscape at Badami 2.09 0.41 Jul, 2018 Jul, 2018 0 CPWD assigned work of project implementation
4 Integrated Development and Improvement of Arterial Road, Transportation Infrastructure, Parking and Road Signage at Badami 13.76 2.75 Aug, 2017 Aug, 2018 15 Work In Progress