4
Projects Approved
₹ 68870818.67Cr.
Total Cost of Approved Projects
₹ 5.39Cr.
Amount Released to City
25.88%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 2. Integrated development and improvement of arterial road transportation infrastructure, parking and signage work at Badami. 64630801.00 2.75 Jul, 2017 Feb, 2019 22.00 Rs. 68214900.00 is approved cost of Entrance arches and Junction Improvement. CPWD has invited tenders.
2 Zero waste management for Badami town. 0.00 1.84 Sep, 2018 Oct, 2018 90.00 Civil works completed 100 % , electrical works works under progress, Bio gas unit, e rikshaw, Mechanical eqipments work order issued .
3 Under ground drainage work for Tatakoti, Badami 4240017.67 0.37 Apr, 2017 Oct, 2018 85.00 Due to ASI prohibitted area, working manually.
4 Improvement of Vernacular building facade and streetscaping 0.00 0.41 Jun, 2016 Jun, 2016 0.00 CPWD has recalled tender.