4
Projects Approved
₹ 21,87,78,813.67 Cr.
Total Cost of Approved Projects
₹ 4,01,08,856.00 Cr.
Amount Released to City
49.47%
Physical Completion

Progress till April 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Integrated development and improvement of arterial road transportation infrastructure, parking and signage work at Badami. 17,69,00,136.00 2,75,37,050.00 Jul, 2017 Mar, 2019 50.00 Final tender cost 176900136 =Rs. 64630801/- (KUIDFC-Road and footpath)+25200000/-( KUIDFC-in lieu of parking plaza tender floated, under evaluation stage)+33842427/-(CPWD- Construction of Arches)+4191494/-(CPWD-Junction improvement)+13993710/-(CPWD-Road signages)+13309160/-(CPWD-Arches and Toilet) ) +21732544/-(CPWD Facade work) Not Inaugurated.
2 Zero waste management for Badami town. 1,59,06,116.00 46,00,000.00 Aug, 2017 Feb, 2019 95.00 Final tender cost :Rs. 15906116 = Civil 8502142/- +Electrical 2189164/- +Mechanical instruments 838990/- +Bio gas unit 3750000/- + e -rikshaw 625820/- Not Inaugurated
3 Under Ground Drainage works for old town of Badami ( for Tatakoti village) 42,40,017.67 37,87,755.00 Apr, 2017 Jan, 2019 100.00 Completed. Not Inaugurated.
4 Improvement of Historic Vernacular Building facade and streetscape at Badami 2,17,32,544.00 41,84,051.00 Oct, 2018 Mar, 2019 2.00 Contractor has started the work. Not Inaugurated
  Total 21,87,78,813.67 4,01,08,856.00