12
Projects Approved
₹ 73,28,10,405.00 Cr.
Total Cost of Approved Projects
₹ 54,01,11,150.00 Cr.
Amount Released to City
67.17%
Physical Completion

Progress till January 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of an Environmental Park at the UBDC Canal at Amritsar 97,62,319.00 79,89,620.00 Oct, 2016 Mar, 2019 50.00 Work in progress
2 Comprehensive road development and up-gradation of 21 major roads leading to Golden Temple at Amritsar. 31,27,32,221.00 29,32,30,661.00 Oct, 2016 Nov, 2018 100.00 Completed
3 Reorganizing Connectivity and Linkages through Streetscape and Landscape improvement at Gol Bagh 4,99,95,177.00 3,79,98,070.00 Oct, 2016 Aug, 2018 100.00 Inaugurated
4 Comprehensive Improvement of a mobility corridor along the outer and inner circular road at Amritsar 4,88,53,006.00 3,89,91,000.00 Oct, 2016 Dec, 2018 75.00 The work of table top crossing and laying of mastic has been completed on Hathi gate rotary, Rambagh gate rotary, Lohgarh gate rotary and Sheranwala gate rotary and work of table top crossing is under progress at Goal Bagh gates and Beautification work of other rotaries and wall is also in progress. The work for construction of Police Museum is being carried out at Ram Bagh Police Station along old wall of the city. This will also be developed as recreational area.
5 Revitalization and Infrastructure Development at 40 Khoo, or 40 Wells and Colonial Period Power House at Amritsar 9,39,26,796.00 3,89,95,252.00 Oct, 2016 Mar, 2019 50.00 Inaugurated , Thr extension of 40Khoo project is in progress
6 Structural retrofitting and up-gradation of the historic fabric of the colonial period building of the current Deputy Commissioner of Amritsar's Office at Amritsar 1,95,24,855.00 1,59,79,420.00 Oct, 2016 Mar, 2019 70.00 Work in Progress
7 Up-gradation of the Maharaja Ranjit Singh Panorama at Amritsar 49,15,144.00 40,11,312.00 Oct, 2016 Sep, 2018 100.00 Completed
8 Landscape Improvements and Historic Edge Delineation of the Rambagh Garden. 1,50,00,000.00 50,20,856.00 Sep, 2018 Dec, 2018 5.20 Work in progress
9 Conservation & Revitalization of Ram Bagh Gate. 2,16,61,587.00 2,67,15,156.00 Oct, 2016 Aug, 2018 100.00 Inaugurated
10 Provision of surface parking in Rambagh Garden 0.00 22,56,403.00 Dec, 2015 Nov, 2018 0.00 Project cancelled as another project in the vicinity was developed by MCA
11 Conservation of historic gates and improvements in the heritage zone 4 - Circular Road- Historic connector 11,89,03,300.00 4,75,61,320.00 Oct, 2018 Mar, 2019 0.00 the actual start date and finish date is tentative since project is not yet tendered.
12 Interpretative Signage in the City with Sensors 3,75,36,000.00 2,13,62,080.00 Oct, 2018 Mar, 2019 0.00 the actual start date and finish date is tentative as the project is being tendered
  Total 73,28,10,405.00 54,01,11,150.00