12
Projects Approved
₹ 61.55Cr.
Total Cost of Approved Projects
₹ 45.38Cr.
Amount Released to City
67.00%
Physical Completion

Progress till February 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Landscape Improvements and Historic Edge Deliniation of the Rambagh Garden 2.51 0.50 0000-00-00 0000-00-00 0 Selection of Contractor to be initiated by ASI.
2 Restoration & Adaptive Reuse of Rambagh Gate 1.08 2.67 Oct, 2016 Jun, 2018 95 Work in Progress
3 Comprehensive road development and up-gradation of 21 major roads leading to Golden Temple at Amritasr 31.99 25.44 Nov, 2016 Jun, 2018 75 Work in Progress
4 Development of Public Plaza along the southern edge of Rambagh Garden at Amritsar 0.99 0.39 Apr, 2018 Apr, 2018 0 Project Cancelled
5 Provision of surface parking at Rambagh gate 1.12 0.22 Apr, 2018 Apr, 2018 0 Project Cancelled
6 Reorganizing Connectivity and Linkages through Streetscape and Landscape improvement at Gol Bagh at Amritsar 4.99 3.79 Nov, 2016 Apr, 2018 95 Work in Progress
7 Comprehensive Improvement of a mobility corridor along the outer and inner circular road at Amritsar 4.99 3.89 Nov, 2016 May, 2018 90 Work in Progress
8 Revitalization and Infrastructure Development at 40 Khoo, or 40 Wells and Colonial Period Power House at Amritsar 4.99 3.89 Nov, 2016 Apr, 2018 95 Work in Progress
9 Development of an Environmental Park at the UBDC Canal at Amritsar 0.99 0.39 Jul, 2017 Jul, 2018 50 Work in Progress
10 Structural retrofitting and up-gradation of the historic fabric of the colonial period building of the current Deputy Commissioner of Amritsar's Office at Amritsar 1.99 1.59 Nov, 2016 Aug, 2018 50 Work in Progress
11 Up-gradation of the Maharaja Ranjit Singh Panorama at Amritsar 0.50 0.40 Nov, 2016 Apr, 2018 95 Work in Progress
12 Interpretative Signage in the City with Sensors 5.34 2.13 0000-00-00 0000-00-00 0 Project divided into two parts: Part 1- Interpretative Signage with Sensors, CPWD is vetting and call the tender by 30th April,2018. Part 2- Paint My City, cost to be revised and thereafter tendered.