10
Projects Approved
₹ 951351165.00Cr.
Total Cost of Approved Projects
₹ 40.06Cr.
Amount Released to City
86.70%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of an Environmental Park at the UBDC Canal at Amritsar 973735.00 0.39 Oct, 2016 Dec, 2018 65.00 Work in progress
2 Comprehensive road development and up-gradation of 21 major roads leading to Golden Temple at Amritsar. 312732221.00 25.44 Oct, 2016 Nov, 2018 70.00 Work in Progress
3 Reorganizing Connectivity and Linkages through Streetscape and Landscape improvement at Gol Bagh 488702855.00 3.79 Oct, 2016 Aug, 2018 100.00 Completed
4 Comprehensive Improvement of a mobility corridor along the outer and inner circular road at Amritsar 48853006.00 3.89 Oct, 2016 Nov, 2018 75.00 Work in Progress
5 Revitalization and Infrastructure Development at 40 Khoo, or 40 Wells and Colonial Period Power House at Amritsar. 48863398.00 3.89 Oct, 2016 Aug, 2018 100.00 Completed
6 Structural retrofitting and up-gradation of the historic fabric of the colonial period building of the current Deputy Commissioner of Amritsar's Office at Amritsar 19974276.00 0.79 Oct, 2016 Dec, 2018 75.00 Work in Progress
7 Up-gradation of the Maharaja Ranjit Singh Panorama at Amritsar. 4915144.00 0.40 Oct, 2016 Sep, 2018 98.00 Whole work is near completion as per scope of work
8 Landscape Improvements and Historic Edge Delineation of the Rambagh Garden. 14936530.00 0.37 Dec, 2015 Nov, 2018 0.00 Work to be executed by ASI. Funds have been deposited by MCA
9 Conservation & Revitalization of Ram Bagh Gate. 11400000.00 0.81 Oct, 2016 Aug, 2018 99.00 Whole the work in scope of work has been completed
10 Provision of surface parking in Rambagh Garden 0.00 0.22 Dec, 2015 Nov, 2018 0.00 Project cancelled as another project in the vicinity was developed by MCA