3
Projects Approved
₹ 199960136.00Cr.
Total Cost of Approved Projects
₹ 12.34Cr.
Amount Released to City
60.23%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Up-gradation of Approach roads to Heritage Sites in Amaravati 100100000.00 10.01 Apr, 2016 Oct, 2018 98.00 The minor strech of 200 meters is left due to issues of private land.
2 Development of Heritage walkway in Amaravathi 23260136.00 2.32 Apr, 2016 Oct, 2018 96.00 Encroachments on the footpaths made and along stretch 1C are high and discussions are in progress at senior executive level for tackling the issue on ground as other state departments are involved. APTDC officials are trying to clear the issue as soon as possible.
3 Redevelopment of the Nunegundam Cheruvu (Amaravathi Pond) 76600000.00 . Sep, 2018 Dec, 2018 0.00 The project is awarded to contractor.