3
Projects Approved
₹ 18,46,60,136.00 Cr.
Total Cost of Approved Projects
₹ 14,36,41,482.00 Cr.
Amount Released to City
80.62%
Physical Completion

Progress till February 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Up-gradation of Approach roads to Heritage Sites in Amaravati 10,01,00,000.00 10,01,00,000.00 Apr, 2016 Dec, 2018 100.00 completed
2 Development of Heritage walkway in Amaravathi 2,32,60,136.00 2,07,93,482.00 Apr, 2016 Feb, 2019 99.00 1st layer of paint along walkway completed , final layer is remaining
3 Redevelopment of the Nunegundam Cheruvu (Amaravathi Pond) 6,13,00,000.00 2,27,48,000.00 Sep, 2018 Apr, 2019 42.00 majority of Work for pond retaining walls completed
  Total 18,46,60,136.00 14,36,41,482.00