Sample Dashboard
2
Projects Approved
₹ 18.75Cr.
Total Cost of Approved Projects
₹ 11.15Cr.
Amount Released to City
30.00%
Physical Completion
Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
Upgradation of approach roads to heritage sites and Development of Heritage walk in amravati 12.33 9.86 Apr, 2016 Dec, 2017 60 Work for approach road completed
Development of Heritage part (Budhhist Park) at Amaravati 6.41 1.28 Apr, 2016 Dec, 2017 0 Land procurement in process