5
Projects Approved
₹ 35.00Cr.
Total Cost of Approved Projects
₹ 19.41Cr.
Amount Released to City
30.00%
Physical Completion

Progress till February 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Bhadrakali Lake Foreshore Development at Warangal 14.94 11.12 Oct, 2015 May, 2018 51 Work In progress
2 Development work at 1000 pillar temple area 0.94 0.18 May, 2016 May, 2018 25 Work In progress
3 Development work at Kazipeth Dargah 1.78 0.35 May, 2016 Sep, 2017 100 Project Completed
4 Rejuvenation of pond at Padmakshi Temple and Development of Jain Sites of Hanamkonda Hill 2.03 1.62 May, 2016 Jun, 2018 48 Work In progress
5 Revival and Development of Fort Warangal 15.29 6.11 Apr, 2016 Nov, 2018 0 MoU was signed between ASI and KUDA. Clearing of Jungle is in progress on rock fort.