5
Projects Approved
₹ 34,99,99,084.00 Cr.
Total Cost of Approved Projects
₹ 19,40,68,581.00 Cr.
Amount Released to City
55.55%
Physical Completion

Progress till January 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development work at Kazipet Dargha 1,78,63,824.00 35,72,765.00 Jun, 2016 Dec, 2016 100.00 Project completed in December 2016 and development is in use.
2 Development work at 1000 pillar temple area 94,00,000.00 18,81,119.00 Jun, 2016 Jan, 2019 50.00 Work like pathways, parking area, landscaping, seating benches, signage, dustbins are in progress
3 Revival and development of Fort Warangal 8,97,00,000.00 6,11,98,127.00 May, 2018 Mar, 2019 5.00 Jungle clearance on the rock fort is completed. revised DPR proposal has been sent to ministry for approval.
4 Bhadrakali Lake Foreshore Bund Development 21,27,00,000.00 11,11,49,518.00 Feb, 2016 Mar, 2019 72.00 Work is in progress. Stone carving work, Landscaping, Granite flooring, etc are in progress.
5 Rejuvenation of Pond at padmakshi Temple & Development of Jain sites on Hanamkonda hill 2,03,35,260.00 1,62,67,052.00 Feb, 2018 Jan, 2019 70.00 Jain sites work is in progress. Padmakshi work is stopped due to the court notice, clearance to be taken from the endowment department.
  Total 34,99,99,084.00 19,40,68,581.00