Projects Approved
₹ 20.00Cr.
Total Cost of Approved Projects
₹ 8.39Cr.
Amount Released to City
20.00%
Physical Completion

Progress till February 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of support infrastructure at Velankkanni Town. 0.97 0.77 Mar, 2016 Nov, 2016 100 Completed
2 Heritage linked infrastructure development of Three Delineated zones (Town Core, Beach Civic & Recreational zone, Transit node) 10.37 4.14 Mar, 2017 May, 2018 30 Work under progress
3 Additional Heritage linked Infrastructure development of 3 Zones 8.66 3.46 Mar, 2018 Jul, 2018 5 Work under progress