10
Projects Approved
₹ 90.15Cr.
Total Cost of Approved Projects
₹ 60.87Cr.
Amount Released to City
56.00%
Physical Completion
Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Construction of 10 approach Roads to various Heritage sites at Varanasi. 7.91 6.33 Jan, 2015 Mar, 2017 75 Work In progress
2 Development of Dashashwamedh- Godowlia Culture Quarter 2.04 0.40 0000-00-00 0000-00-00 0 Project on Hold/Cancelled
3 Redevelopment of Town Hall as Heritage Centre 2.58 2.02 Aug, 2016 May, 2017 70 Work In progress
4 Development of 24 Roads leading to various Heritage Sites at Varanasi. 29.89 21.69 Apr, 2016 Jun, 2017 85 Work In progress
5 Development of Heritage precinct of Road Connecting Durgakund, Kurushetra Pokhra and Assi Ghat at Varanasi 1.86 1.42 Nov, 2016 Jul, 2017 80 Work In progress
6 Carrying out Heritage Artistic Paint Work at Varanasi. 0.07 0.07 Nov, 2017 Nov, 2017 100 Completed
7 Heritage Walk around Kabir Chaura and Piplani Katra 2.51 1.00 Jan, 2017 Dec, 2017 50 Work In progress
8 Development of 86 heritage sites of Varanasi 10.75 4.30 Dec, 2016 Oct, 2017 70 Work In progress
9 LED street light for Old Kashi Zone 26.50 21.20 Mar, 2017 Sep, 2017 25 Work In progress
10 Thematic Development of 10 Aapproach roads 6.00 2.40 Jul, 2017 Jan, 2018 5 Work In progress