10
Projects Approved
₹ 512759276.89Cr.
Total Cost of Approved Projects
₹ 51.12Cr.
Amount Released to City
96.51%
Physical Completion

Progress till June 2018

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Construction and Repair of 24 Roads in Varanasi under HRIDAY Scheme 26.28 . May, 2016 Mar, 2018 100.00 Work has been completed .
2 Thematic development of 10 HRIDAY Roads 6.61 2.40 Feb, 2018 Nov, 2018 13.00 Work is in progress.
3 Redevelopment of town hall as heritage centre at varanasi 22600000.00 2.26 Sep, 2016 May, 2018 100.00 Work has been completed and inaugurated by honorable Prime Minister on 14/07/2018
4 Development of Heritage precinct of Road connecting Durgakund kurushetra pokhra and Assi Ghat 14597010.00 1.42 Sep, 2016 Feb, 2018 100.00 work has been Completed and inaugurated by honorable Prime Minister on 14/07/2018
5 Heritage walk around Kabir Chaura & Piplani Katra at Varanasi 23065467.00 2.30 Dec, 2016 Jul, 2018 100.00 Work has been Completed and inaugurated by honorable Prime Minister on 14/07/2018
6 Redevelopment of 10 approach roads to various heritage sites of Varanasi. 77971032.00 7.91 Dec, 2015 Nov, 2017 100.00 Work has been completed and inaugurated by honorable Prime Minister on 14/07/2018
7 Development of 86 heritage sites of Varanasi 94370155.00 8.39 Dec, 2016 Oct, 2018 96.00 78 Sites have been completed. One site Padini kanya Mahavidyalay will be completed by 30-09-2018. Remaining two sites Pitrakund and Sankatmochan Gate can be completed by 15 Oct 2018. Above two works are delayed due to rain.
8 Heritage Artistic Paint work at varanasi 315989.00 0.07 Feb, 2016 Feb, 2016 100.00 work is completed..
9 Devlopment of Dashaswamedh Gowdowlia cultural Quater 14839591.00 0.40 Sep, 2016 Oct, 2030 5.00 Work has been cancelled and taken by Tourism department under Prasad Scheme.
10 Heritage Led Street Lighting 265000000.00 25.92 May, 2017 Mar, 2018 100.00 Work has been completed.