10
Projects Approved
₹ 89.15Cr.
Total Cost of Approved Projects
₹ 68.38Cr.
Amount Released to City
89.00%
Physical Completion

Progress till February 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Construction of 10 approach Roads to various Heritage sites at Varanasi. 7.91 7.91 Jan, 2015 Jan, 2018 100 Completed
2 Redevelopment of Town Hall as Heritage Centre 2.58 2.02 Aug, 2016 Apr, 2018 95 Work In progress
3 Development of 24 Roads leading to various Heritage Sites at Varanasi. 29.89 21.69 Apr, 2016 Jan, 2018 100 Completed
4 Development of Heritage precinct of Road Connecting Durgakund, Kurushetra Pokhra and Assi Ghat at Varanasi 1.86 1.42 Nov, 2016 Apr, 2018 98 Work In progress
5 Carrying out Heritage Artistic Paint Work at Varanasi. 0.07 0.07 Apr, 2018 Apr, 2018 100 Completed
6 Heritage Walk around Kabir Chaura and Piplani Katra 2.51 1.81 Jan, 2017 Apr, 2018 80 Work In progress
7 Development of 86 heritage sites of Varanasi 10.75 9.40 Dec, 2016 Apr, 2018 90 Work In progress
8 LED street light for Old Kashi Zone 26.50 21.20 Mar, 2017 Apr, 2018 98 Work In progress
9 Thematic Development of 10 Aapproach roads 6.00 2.40 Jul, 2017 Jun, 2018 25 Work In progress
10 Fa├žade Lighting for Historic monument of Town Hall and Durga Mandir 1.03 0.41 Dec, 2017 Apr, 2018 70 Work In progress