Projects Approved
₹ 35.43Cr.
Total Cost of Approved Projects
₹ 26.00Cr.
Amount Released to City
55.00%
Physical Completion

Progress till February 2018

Sr. No. Name of Project Approved Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Development of Heritage Walk connecting Akbari Quila and Soni ji ki Nasiya for Ajmer. 5.72 4.41 Mar, 2016 Jul, 2018 65 Work in Progress
2 Development of Jaipur Road Precinct at Ajmer 3.54 0.70 Sep, 2016 Jun, 2018 30 Work in Progress
3 Development of Pushkar Heritage Walk at Ajmer 6.16 4.92 Sep, 2016 Jul, 2018 55 Work in Progress
4 Development of Subhash Udyan at Ajmer 8.30 6.58 Sep, 2016 Aug, 2018 60 Work in Progress
5 Annasagar Lakefront Up-gradation at Ajmer 11.69 9.35 Sep, 2016 Sep, 2018 55 Work in Progress